DATE
|
DEPARTMENTAL ACTION/ PROJECT DESCRIPTION & CHANGES
|
|
April 1998
|
Board of Supervisors directed Planning Commission to work
with Radford Planning Commission on a joint Comprehensive
Plan amendment for the Corridor Area on the south side of
Interstate-81. |
|
|
Joint work session scheduled for June 17th with Radford
Planning Commission to discuss joint Comprehensive plan
amendment for the Corridor Area on the south side of Interstate-81 |
|
|
Work session with the Radford Planning Commission rescheduled
for September |
|
September 1998
|
Held joint Work Session with Radford Planning Commission. Planning staff
to work with Planning District Commission staff to develop timetalbe and
cost estimate for an Amendment to the Joint
Comprehensive Plan for the Corridor Area (1993). |
| October 1998 |
Contract with Planning District Commission to prepare
amendment to the Joint Comprehensive Plan for the Corridor
Area (1993) approved by the Planning Commission and the
Board of Supervisors. Awaiting approval by Radford. |
| November 1998 |
Contract with Planning District Commission approved by
Radford Planning Commission but tabled by Radford City Council. |
| June 1999 |
Following an earlier meeting between the Radford Mayor,
the Radford City Manager, the Montgomery County Board of
Supervisors Chairman, and the County Administrator, the
Radford City Council approved proceeding with revision of
the Joint Comprehensive Plan for the Corridor Area. Met
with Planning District Commission staff to prepare revised
contract for proceeding with the work. |
| August 1999 |
Revised Scope of Work received from the New River Valley
Planning District Commission (NRVPDC). |
| September 1999 |
Contract executed between NRVPDC, Radford, and Montgomery
County to conduct study update. Steering Committee held
first monthly meeting to organize. |
| October 1999 |
Steering Committee Meeting: highway and water & sewer
issues. |
| November 1999 |
Steering Committee Meeting: future development plans and
emergency services for the corridor. |
| December 1999 |
Steering Committee Meeting |
| January 2000 |
Steering Committee Meeting: planned agenda for public
information meeting to be held on February 2nd, 2000. |
| February 2000 |
Public information meeting to receive citizen input held
on February 2nd at Bethel School. Steering Committee Meeting:
discussed results from public information meeting. |
| March 2000 |
Steering Committee Meeting: land use issues |
| April 2000 |
Steering Committee Meeting: sewer issues with Charlie
Maus (Peppers Ferry Regional Wastewater Authority) and Michael
Kirk (Montgomery County Public Service Authority). |
| May 2000 |
Steering Committee Meeting: sewer issues with Jettie Montgomery
(Radford City) |
| June 2000 |
Steering Committee Meeting: future land use issues |
| July 2000 |
Steering Committee Meeting: future land use issues. Public
information meeting tentatively secheduled for September. |
| August 2000 |
Steering Committee Meeting: draft future land use plan
and draft report. Public information meeting scheduled for
September 21st. |
| September 2000 |
Public information meeting held at Bethel Elementary School
on September 21st. |
| Ocober 2000 |
Steering Committee held two meetings to complete discussion
of comments from public meeting and made final recommendations
on future land use plan and report to the two Planning Commissions
(Radford and Montgomery County). |
| November 2000 |
Montgomery County Planning Commission reviewed Comprehensive
Plan amendments to implement study recommendations and scheduled
public hearing for December 6th. |
| December 2000 |
Montgomery County Planning Commission held public hearing
and recommended approval of the Comprehensive Plan amendments
to implement study recommendations. Staff met with Radford
and NRVPDC representatives to work on amending impervious
surface requirement in the 1999 Zoning Ordinance. |
| January 2001 |
Montgomery County Board of Supervisors schedule a public
hearing on the Comprehensive Plan amendments for February
22nd. |
| February 2001 |
Montgomery County Board of Supervisors held a public hearing
on the Comprehensive Plan amendments on the 22nd. |
| March 2001 |
Comprehensive Plan amendments are approved by the Montgomery
County Board of Supervisors. Awaiting approval by Radford
City Council. |
| May 2001 |
Comprehensive Plan amendments are approved by the Radford
City Council.
|
| June, 2001 |
Radford City Council asked for a joint meeting
with Board of Supervisors on the Study Update. Meeting scheduled
for July 30th. |
| July, 2001 |
Supervisors held joint work session with Radford
City Council to review and discuss study recommendations. |